146,47 M3 Lumpur Berhasil Dikeruk di PHB Sulaiman

Dredging Work is Conducted at Sulaiman Connecting Channel in Kebon Jeruk

Kebon Jeruk Sub-district Water Resources (SDA) Unit, West Jakarta, dredged Sulaiman connecting (phb) channel on Jl. Yusuf. From this dredging work, personnel collected 146.47 cubic meters of mud.

Our target is to finish the dredging work in July 2021

Kebon Jeruk Sub-district SDA Unit Head, Suprapto conveyed, Sulaiman phb channel has total length of 744 meters, while current work has reached 320 meters. This work has been carried out since May 3, 2021.

"Our target is to finish the dredging work in July 2021," he stated, Monday (6/28).

Kali Sunter River Normalization Enters Land Acquisition Stage

According to him, mud thickness in Sulaiman phb channel reached around 100 centimeters to 1 meter. TIn this dredging work, 36 Kebon Jeruk Sub-district SDA Unit personnel and 10 PPSU personnel were deployed to clean up channel manually using hoe, bucket, crowbar, and cart.

"Dredging will optimize channel's capacity thus it can hold more water, especially when heavy rain falls. Besides, it is hoped to minimize inundation in the surrounding area," he explained.

Linked News
Popular News indeks
  1. Open for All: Jakarta City Hall Welcomes Visitors for Namu Balai Kota

    access_time03-10-2026 remove_red_eye680 personDessy Suciati
  2. Transjakarta Reaffirms Ban on Busking in Mikrotrans and Bus Stops

    access_time02-10-2026 remove_red_eye510 personAldi Geri Lumban Tobing
  3. Jakarta Builds Five New Animal Health Centers to Expand Veterinary Services

    access_time30-09-2026 remove_red_eye506 personAldi Geri Lumban Tobing
  4. Commission D Supports Reserve Fund for Long-Term Infrastructure

    access_time02-10-2026 remove_red_eye481 personFakhrizal Fakhri
  5. 1,500 Runners and Pets Hit the Track for World Rabies Day Run 2026

    access_time03-10-2026 remove_red_eye471 personAnita Karyati